Flood Control and Drainage24A00248

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF RIVERBANK PROTECTION ALONG AGNO RIVER BASIN, BARANGAY UMANDAY, BUGALLON, PANGASINAN

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF RIVERBANK PROTECTION ALONG AGNO RIVER BASIN, BARANGAY UMANDAY, BUGALLON, PANGASINAN is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱48,249,737.08. Status: Past target date (DPWH On-Going). Contractor on record: ANORE CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

120 projects · ₱11.6B total · 12 flags

Other projects by this contractor

No sat.

REHABILITATION OF NORTH NAVOTAS PUMPING STATION AND NAVOTAS NAVIGATION GATE (PHASE 3), NAVOTAS CITY (RE-ADVERTISEMENT)

National Capital Region, National Capital Region

2024₱281.2M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (DOWNSTREAM LS), PACKAGE C, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱276.1M
Past target date (DPWH On-Going)
No sat.

COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF COASTAL ROAD, BRGY. SAN ANTONIO SECTION, NAUJAN, ORIENTAL MINDORO

Region IV-B, Region IV-B

2025₱276.1M
Past target date (DPWH On-Going)
No sat.

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONST. OF ROAD DIKE, PANGALAAN RIVER, BRGY. TIGKAN SECTION (LS), PACKAGE B, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱276.0M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF LIGAYA-STA. LUCIA COASTAL ROAD (STA. LUCIA SECTION), SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱247.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ILVITA RIVERBANK PROTECTION WORKS ALONG AMNAY RIVER (DOWNSTREAM), SABLAYAN, OCC. MINDORO

Region IV-B, Region IV-B

2024₱238.3M
Past target date (DPWH On-Going)
View all 120 projects →

4. Implementation

Contract Amount

₱48,249,737.08

Progress

Past target date (DPWH On-Going)

Start Date

March 11, 2024

Target End

January 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.