Roads23AI0166

CONCRETING OF BRGY. SOBOL TO BRGY. CALEPAAN FMR, BRGY. SOBOL AND BRGY. CALEPAAN, ASINGAN, PANGASINAN

CONCRETING OF BRGY. SOBOL TO BRGY. CALEPAAN FMR, BRGY. SOBOL AND BRGY. CALEPAAN, ASINGAN, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱11,926,912.00. Status: Reported complete (DPWH). Contractor on record: A P TAGARINO ENGINEERING AND CONST SERVICES. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Mitura River, Brgy.Sobol - Brgy. Toboy, Asingan, Pangasinan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Pangasinan 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,926,912.00

Progress

Reported complete (DPWH)

Start Date

June 7, 2023

Target End

September 19, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.