Buildings and Facilities18DL0023

CLUSTER IIIA. 2. LOCAL INFRASTRUCTURE PROGRAM A. BUILDINGS AND OTHER STRUCTURES 1. MULTIPURPOSE / FACILITIES 4. CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. MAUNLAD, GUMACA, QUEZON - P 1,959,751.07B. 2. LOCAL INFRASTRUCTURE PROGRAM A. BUILDINGS AN

CLUSTER IIIA. 2. LOCAL INFRASTRUCTURE PROGRAM A. BUILDINGS AND OTHER STRUCTURES 1. MULTIPURPOSE / FACILITIES 4. CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. MAUNLAD, GUMACA, QUEZON - P 1,959,751.07B. 2. LOCAL INFRASTRUCTURE PROGRAM A. BUILDINGS AN is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱4,799,644.43. Status: Reported complete (DPWH). Contractor on record: R A MENDIOLA CONST. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structures along Sangirin River, Brgy. Sangirin, Perez, Quezon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Quezon 4th DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

467 projects · ₱8.0B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 14. CONSTRUCTION OF ROAD, GUMACA, QUEZON,

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES 18. CONSTRUCTION/IMPROVEMENT OF ACCESS ROAD

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 15. CONSTRUCTION/IMPROVEMENT OF ACCESS ROA

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 16. CONSTRUCTION OF ROAD, GUINAYANGAN, QUE

Quezon 4th DEO, Region IV-A

2023₱106.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL, BARANGAY 1 AND BARANGAY 5, CATANAUAN, QUEZON

Quezon 3rd DEO, Region IV-A

2024₱101.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM, ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES 7. CONSTRUCTION OF LOPEZ -MACALELON ROAD, PACKAGE E, LOPEZ, QUEZON

Quezon 4th DEO, Region IV-A

2023₱99.0M
Reported complete (DPWH)
View all 467 projects →

4. Implementation

Contract Amount

₱4,799,644.43

Progress

Reported complete (DPWH)

Start Date

February 20, 2018

Target End

May 20, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.