Buildings and Facilities24OF0182

CONSTRUCTION OF MULTI-PURPOSE BUILDING, WEST SIDE, BARANGAY COMMONWEALTH, QUEZON CITY

CONSTRUCTION OF MULTI-PURPOSE BUILDING, WEST SIDE, BARANGAY COMMONWEALTH, QUEZON CITY is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱5,880,500.80. Status: Reported complete (DPWH). Contractor on record: EURO CONST AND SUPPLY FORMERLY: EURO CONST AND TRADING 39267. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure at Barangay Payatas, Quezon City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quezon City 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 39267

27 projects · ₱319.3M total · 0 flags

4. Implementation

Contract Amount

₱5,880,500.80

Progress

Reported complete (DPWH)

Start Date

June 13, 2024

Target End

January 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.