Construction of Flood Mitigation Structure23DD0023

Construction of Flood Control Structure, Pinagsibaan Bridge 2, Rosario, Batangas

Construction of Flood Control Structure, Pinagsibaan Bridge 2, Rosario, Batangas is a DPWH-tracked public work in ROSARIO (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱29,400,000.00. Status: Reported complete (DPWH). Contractor on record: TONIJON CONST AND DEVELOPMENT INC FORMERLY: TONIJON CONST. Figures trace to sumbong.

ROSARIO (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Pinagsibaan Bridge 2, Rosario, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 4th District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Reported complete (DPWH)

Start Date

February 8, 2023

Target End

July 1, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.