Roads15KJ0092

REHAB/RECONST/UPGRADING OF DAMAGE PAVED NATIONAL ROADS INCL DRAINAGE, TAN AVENUE ROAD K1686+17-K1686+400, K1686+691-K1687+0

REHAB/RECONST/UPGRADING OF DAMAGE PAVED NATIONAL ROADS INCL DRAINAGE, TAN AVENUE ROAD K1686+17-K1686+400, K1686+691-K1687+0 is a DPWH-tracked public work in Misamis Occidental 2nd DEO, Region X. Reported contract value: ₱23,577,339.37. Status: Reported complete (DPWH). Contractor on record: MINDANAO ROCK 23479. Figures trace to dpwh.

Misamis Occidental 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱23,577,339.37

Progress

Reported complete (DPWH)

Start Date

March 22, 2016

Target End

August 9, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.