Buildings and Facilities25K00023

CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUNICIPAL GYM, MADALUM, LANAO DEL SUR

CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUNICIPAL GYM, MADALUM, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱29,635,268.86. Status: Past target date (DPWH On-Going). Contractor on record: AL YUSOPH CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱29,635,268.86

Progress

Past target date (DPWH On-Going)

Start Date

March 17, 2025

Target End

September 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.