Flood Control and Drainage20DB0083

CONSTRUCTION OF SEAWALL/ RIPRAPPING, BRGY. LUMANIAG, LIAN, BATANGAS

CONSTRUCTION OF SEAWALL/ RIPRAPPING, BRGY. LUMANIAG, LIAN, BATANGAS is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱1,000,000.00. Status: Reported complete (DPWH). Contractor on record: 6 JEWELS CONST. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,000,000.00

Progress

Reported complete (DPWH)

Start Date

October 16, 2020

Target End

December 14, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.