Flood Control and Drainage23CL0031

CONSTRUCTION OF SLOPE PROTECTION ALONG BOTOLAN-CAPAZ ROAD (PHASE 2), BOTOLAN, ZAMBALES

CONSTRUCTION OF SLOPE PROTECTION ALONG BOTOLAN-CAPAZ ROAD (PHASE 2), BOTOLAN, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱59,856,105.11. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MINDANAO ROCK. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Batonlapoc Creek, Batonlapoc, Botolan, Zambales
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zambales 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱59,856,105.11

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 23, 2023

Target End

January 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.