GAA 2023 OO-223K00183

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ACACIA EXTENSION, CARMEN, CAGAYAN DE ORO CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ACACIA EXTENSION, CARMEN, CAGAYAN DE ORO CITY is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱16,953,858.95. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RBT VENTURES. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱16,953,858.95

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

November 23, 2023

Target End

May 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.