Flood Control and Drainage16OG0011

CONSTRUCTION / REHABILITATION OF DRAINAGE SYSTEM ALONG CAMP AGUINALDO ROAD NETWORK (PHASE I) QC 3RD

CONSTRUCTION / REHABILITATION OF DRAINAGE SYSTEM ALONG CAMP AGUINALDO ROAD NETWORK (PHASE I) QC 3RD is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱18,385,542.20. Status: Reported complete (DPWH). Contractor on record: HEXAMINDZ CORP FORMERLY:KILUSANG MAGKAIBIG. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures and Tributaries at Brgy. Payatas, (Phase 2) District II, Quezon City
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-16-0020569

₱358,949.00 · FY2016

Released to 00 - Don Mariano Marcos Memorial State University To cover re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱18,385,542.20

Progress

Reported complete (DPWH)

Start Date

February 26, 2016

Target End

August 13, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.