GAA 2017 MFO-117I00016

CONSTRUCTION OF BY-PASSES / DIVERSION ROADS, INCLUDING ROW, SAN ROQUE BY-PASS ROAD, NORTHERN SAMAR 2ND LD

CONSTRUCTION OF BY-PASSES / DIVERSION ROADS, INCLUDING ROW, SAN ROQUE BY-PASS ROAD, NORTHERN SAMAR 2ND LD is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱94,613,737.57. Status: Reported complete (DPWH). Contractor on record: ESD CRUZ CONST & SUPPLY. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱94,613,737.57

Progress

Reported complete (DPWH)

Start Date

March 30, 2017

Target End

June 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.