Buildings and Facilities22CJ0130

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES COMPLETION OF MULTI PURPOSE BUILDING AT BARANGAY SALAPUNGAN, GERONA, TARLAC

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES COMPLETION OF MULTI PURPOSE BUILDING AT BARANGAY SALAPUNGAN, GERONA, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱1,929,882.33. Status: Reported complete (DPWH). Contractor on record: D D GUINTU CONST. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure Along Tarlac River Control Left Dike, Sembrano - Sta. Lucia Section (Phase IV), Gerona, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Tarlac DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱1.9M total · 0 flags

4. Implementation

Contract Amount

₱1,929,882.33

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

May 28, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.