Roads17GF0026

RECONSTRUCTION FROM CONCRETE TO CONCRETE - TIOLAS-SINUGBUHAN ROAD INCLUDING RROW, K0062+197 - K0062+325; K0063+030 - K0063+463; K0065+000 - K0065+540; K0065+754 - K0065+820; K0066+711 - K0066+782; K0066+782 - K0066+904; K0066+904 - K0066+999; K066+999 - K

RECONSTRUCTION FROM CONCRETE TO CONCRETE - TIOLAS-SINUGBUHAN ROAD INCLUDING RROW, K0062+197 - K0062+325; K0063+030 - K0063+463; K0065+000 - K0065+540; K0065+754 - K0065+820; K0066+711 - K0066+782; K0066+782 - K0066+904; K0066+904 - K0066+999; K066+999 - K is a DPWH-tracked public work in Iloilo 1st DEO, Region VI. Reported contract value: ₱42,817,279.97. Status: Reported complete (DPWH). Contractor on record: AFG ZILLION CONST CORP FORMERLY: A F G CONST. Figures trace to dpwh.

Iloilo 1st DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Jarao Flood Control Project, Particion, Guimbal, Iloilo
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0014363

₱15,000.00 · FY2017

Released to Gabi National High RL School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

207 projects · ₱2.6B total · 0 flags

4. Implementation

Contract Amount

₱42,817,279.97

Progress

Reported complete (DPWH)

Start Date

October 18, 2017

Target End

April 5, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.