Flood Control and Drainage25DQ0013

CONSTRUCTION OF SLOPE PROTECTION AND FLOOD PROTECTION STRUCTURE ALONG CARMONA RIVER, PHASE 2, CARMONA, CAVITE

CONSTRUCTION OF SLOPE PROTECTION AND FLOOD PROTECTION STRUCTURE ALONG CARMONA RIVER, PHASE 2, CARMONA, CAVITE is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱48,411,935.08. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: OMNICON BUILDERS 22816. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection and Flood Protection Structure along Carmona River, Phase 2, Carmona, Cavite
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cavite 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,411,935.08

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 17, 2025

Target End

October 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.