Roads22HB0044

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD AT BARANGAY NAN-OD,

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD AT BARANGAY NAN-OD, is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱4,801,916.10. Status: Reported complete (DPWH). Contractor on record: WBV CONST. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱41,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Loboc River, Villaflor, Loboc , Bohol
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bohol 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

37 projects · ₱205.8M total · 0 flags

4. Implementation

Contract Amount

₱4,801,916.10

Progress

Reported complete (DPWH)

Start Date

April 11, 2022

Target End

May 27, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.