Buildings and Facilities23J00211

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MALANTA, SAPA-SAPA, TAWI-TAWI

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MALANTA, SAPA-SAPA, TAWI-TAWI is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱14,469,985.71. Status: Past target date (DPWH On-Going). Contractor on record: BCH IZONARL CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,469,985.71

Progress

Past target date (DPWH On-Going)

Start Date

May 17, 2023

Target End

February 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.