Bridges23IJ0055

CSSP: CONSTRUCTION OF BRIDGE, PHASE 1, BARANGAY NALIHUGAN, GANDARA, WESTERN SAMAR

CSSP: CONSTRUCTION OF BRIDGE, PHASE 1, BARANGAY NALIHUGAN, GANDARA, WESTERN SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱39,388,279.79. Status: Past target date (DPWH On-Going). Contractor on record: CDU CONST 13915. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project, Gandara, Samar
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Samar 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 13915

325 projects · ₱8.8B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0861+453 - K0862+355, K0862+380 - K0862+786, K0863+064 - K0863+364, K0863+600 - K0863+685, K0863+685 -

Region VIII, Region VIII

2025₱151.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0734+578 - K0735+526, K0742+826 - K0745+000, SAMAR 1ST LD

Region VIII, Region VIII

2024₱147.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MAROYONDOYON CREEK & KAGLANGKOY CREEK, CATARMAN, NORTHERN SAMAR

Northern Samar 1st DEO, Region VIII

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

VIILP - LOCAL ROADS AND BRIDGES - LOCAL ROADS - ROAD OPENING / CONCRETING OF HINANGUTDAN, STA. RITA TO SAN ROQUE, VILLAREAL, SAMAR (PHASE I)

Region VIII, Region VIII

2020₱136.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM- (KATUPARAN)- ITBAYAT AIRPORT /NIA CIRCUMFERENTIAL ROAD, ITBAYAT, BATANES

Region II, Region II

2022₱106.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - ROAD OPENING/CONCRETING OF HINANGUTDAN - STA. RITA TO SAN ROQUE - VILLAREAL, SAMAR (PHASE III), SAMAR 2ND LD

Region VIII, Region VIII

2021₱99.4M
Reported complete (DPWH)
View all 325 projects →

4. Implementation

Contract Amount

₱39,388,279.79

Progress

Past target date (DPWH On-Going)

Start Date

May 31, 2023

Target End

November 20, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.