Flood Control and Drainage21LA0148

CONSTRUCTION OF REVETMENT ALONG HIJO RIVER AT BARANGAY NEW ASTURIAS, MACO, DAVAO DE ORO

CONSTRUCTION OF REVETMENT ALONG HIJO RIVER AT BARANGAY NEW ASTURIAS, MACO, DAVAO DE ORO is a DPWH-tracked public work in Davao de Oro 1st DEO, Region XI. Reported contract value: ₱19,599,975.53. Status: Reported complete (DPWH). Contractor on record: FORTSTONE CONST ENT. Figures trace to dpwh.

Davao de Oro 1st DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱7,018,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Padada Mainit River, Sta. 0+000 - Sta. 0+140, Davao del Sur
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Davao de Oro 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,599,975.53

Progress

Reported complete (DPWH)

Start Date

July 12, 2021

Target End

February 23, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.