Buildings and Facilities21OB0117

CONSTRUCTION (COMPLETION) OF TWO (2) STOREY RHSU BUILDING (PHASE II), CAMP BAGONG DIWA, TAGUIG CITY

CONSTRUCTION (COMPLETION) OF TWO (2) STOREY RHSU BUILDING (PHASE II), CAMP BAGONG DIWA, TAGUIG CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱4,752,772.70. Status: Reported complete (DPWH). Contractor on record: JAYLOT TRADING. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱11,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Sapang Baho, Marikina City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Metro Manila 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,752,772.70

Progress

Reported complete (DPWH)

Start Date

March 23, 2021

Target End

July 20, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.