Roads18HF0083

REHABILITATION/RECONSTRUCTION OF TOLEDO-TABUELAN-SN REMIGIO RD WITH SLIPS - K0050+388-K0050+600, K0059+236-K0059+306, K0101 + 834-K0102+334, K0102+537-K0102+707

REHABILITATION/RECONSTRUCTION OF TOLEDO-TABUELAN-SN REMIGIO RD WITH SLIPS - K0050+388-K0050+600, K0059+236-K0059+306, K0101 + 834-K0102+334, K0102+537-K0102+707 is a DPWH-tracked public work in Cebu 3rd DEO, Region VII. Reported contract value: ₱43,947,119.40. Status: Reported complete (DPWH). Contractor on record: QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST. Figures trace to dpwh.

Cebu 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment (rubble conrete) at Guinabasan river basin along Toledo-Tabuelan-San Remigio Road, Brgy. Sta. Lucia, Asturias, Cebu
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVB-18-0019685

₱622,420.00 · FY2018

Released to Mabini National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

409 projects · ₱18.8B total · 42 flags

Other projects by this contractor

No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF COASTAL ROAD, PHASE 1, BARANGAY IBO, LAPULAPU CITY, CEBU

Region VII, Region VII

2024₱231.5M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TIPOLO RIVER, PHASE 4, MANDAUE CITY

Region VII, Region VII

2025₱202.5M
Past target date (DPWH On-Going)
No sat.

CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANTAYUPAN ROAD (LEADING TO BANGAG LAPOS CAVE), BARILI, CEBU

Region VII, Region VII

2024₱178.2M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST OF FLOOD CONTROL STRUCTURE ALONG MANANGA RIVER (UPSTREAM), TALISAY CITY, CEBU

Region VII, Region VII

2024₱173.7M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF BABAG-BASAK-SUBABASBAS BYPASS ROAD, LAPU-LAPU CITY

Region VII, Region VII

2024₱173.7M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MARIGONDON-BASAK BYPASS ROAD, LAPU-LAPU CITY, CEBU

Region VII, Region VII

2024₱173.6M
Past target date (DPWH On-Going)
View all 409 projects →

4. Implementation

Contract Amount

₱43,947,119.40

Progress

Reported complete (DPWH)

Start Date

April 9, 2018

Target End

March 23, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.