Construction of Flood Mitigation Structure22EI0112

Construction of Flood Mitigation Structure Cagancan River, Brgy Don Pedro, Mansalay, Oriental Mindoro

Construction of Flood Mitigation Structure Cagancan River, Brgy Don Pedro, Mansalay, Oriental Mindoro is a DPWH-tracked public work in MANSALAY (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱24,749,532.40. Status: Reported complete (DPWH). Contractor on record: D M MALIWANAG BUILDERS AND ENT. Figures trace to sumbong.

MANSALAY (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure Cagancan River, Brgy Don Pedro, Mansalay, Oriental Mindoro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002623

₱812,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003190

₱725,980,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-22-0005756

₱150,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002624

₱49,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003023

₱10,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱24,749,532.40

Progress

Reported complete (DPWH)

Start Date

July 20, 2022

Target End

March 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.