Roads17CG0138

CONCRETING OF SAN ISIDRO FMR, BRGY. SAN ISIDRO, SAN LUIS, PAMPANGA STA. 0+000-STA. 0+369, SAN LUIS, PAMPANGA

CONCRETING OF SAN ISIDRO FMR, BRGY. SAN ISIDRO, SAN LUIS, PAMPANGA STA. 0+000-STA. 0+369, SAN LUIS, PAMPANGA is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱1,876,566.00. Status: Reported complete (DPWH). Contractor on record: MARKNEST CONST AND TRADING FORMERLY MARKNE 16818. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,876,566.00

Progress

Reported complete (DPWH)

Start Date

September 13, 2017

Target End

October 27, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.