Buildings and Facilities25CC0183

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUNGAHAN, MALOLOS CITY, BULACAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUNGAHAN, MALOLOS CITY, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱9,697,984.67. Status: Past target date (DPWH On-Going). Contractor on record: EARTHWORK BUILDERS INC FORMERLY: EARTHWORK MOVERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure with Pumping Station and Flood Gate at Barangay Santo Rosario Creek, Malolos City, Bulacan (Phase III)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,697,984.67

Progress

Past target date (DPWH On-Going)

Start Date

March 21, 2025

Target End

September 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.