Buildings and Facilities24BD0167

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY MASICAL, AMULUNG, CAGAYAN

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI-PURPOSE BUILDING AT BARANGAY MASICAL, AMULUNG, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱2,450,718.08. Status: Reported complete (DPWH). Contractor on record: V R D J CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Cagayan River Flood Management Projects, Baccuit, Amulung, Cagayan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cagayan 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

21 projects · ₱57.5M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN MATUSALEM ELEMENTARYSCHOOL, BARANGAY MATUSALEM, ROXAS, ISABELA

Isabela 2nd DEO, Region II

2024₱4.9M
Reported complete (DPWH)
No sat.

PROVISION OF TECH VOC WORKSHOP BLDGS./LABORATORIES FOR SENIOR HIGH SCHOOL/CONST'N OF TECNICAL-VOCATIONAL-LIVELIHOOD (TVL) LABORATORIES/WORKSHOP FOR SENIOR HS (2 UNITS-UNIQUE WORKSHOP (UW) @ SAN ANTONIO NAT'L HIGH SCHOOL, DELFIN ALBANO (MAGSAYSAY), ISABE

Isabela 1st DEO, Region II

2016₱4.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ONE - STOREY THREE (3) CLASSROOM SCHOOL BUILDING (1STY3CL) AT STA. CRUZ MULTIGRADE, DELFIN ALBANO (MAGSAYSAY), ISABELA

Isabela 1st DEO, Region II

2017₱3.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS) SAN JUAN RUGAO E/S, CITY OF ILAGAN, ISABELA , MARANA 2ND E/S, CITYOF ILAGAN, ISABELA, STA. ISABEL SUR E/S, CITY OF ILAGAN, ISABELA, SALINDINGAN E/S, CITY OF ILAGAN, ISABELA, FUGU E/S, CITY OF ILAGAN, IS

Isabela 1st DEO, Region II

2018₱3.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS) I. REINFORCED STEEL GROUND STORAGE TANK: (1) BALASIG E/S, CABAGAN, ISABELA (2) MAGASSI H/S, CABAGAN, ISABELA (3) UNION E/S, CABAGAN, ISABELA (4) PILIG ABAJO E/S, CABAGAN, ISABELA (5) ALINGUIGAN 2ND E/S,

Isabela 1st DEO, Region II

2017₱3.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF TECHNICAL-VOCATIONAL-LIVELIHOOD (TVL) UNIQUE WORKSHOP AT DELFIN ALBANO NATIONAL HS, CABAGAN, ISABELA

Isabela 1st DEO, Region II

2017₱3.0M
Reported complete (DPWH)
View all 21 projects →

4. Implementation

Contract Amount

₱2,450,718.08

Progress

Reported complete (DPWH)

Start Date

July 25, 2024

Target End

November 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.