CONSTRUCTION OF MISSING LINKS/NEW ROADS, BONIFACIO-DON VICTORIANO ROAD (PETIANAN-BAGONG CLARIN SECTION) MISAMIS OCCIDENTAL

CONSTRUCTION OF MISSING LINKS/NEW ROADS, BONIFACIO-DON VICTORIANO ROAD (PETIANAN-BAGONG CLARIN SECTION) MISAMIS OCCIDENTAL is a DPWH-tracked public work in Misamis Occidental 2nd DEO, Region X. Reported contract value: ₱91,675,564.67. Status: Reported complete (DPWH). Contractor on record: MINDANAO ROCK 23479. Figures trace to dpwh.

Misamis Occidental 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱91,675,564.67

Progress

Reported complete (DPWH)

Start Date

May 14, 2018

Target End

October 15, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.