GAA 2020 CSSP20HB0001

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONST./IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION, VILLAFLOR CIRCUMFERENTIAL ROAD LEADING TO LOBOC RIVERCRUISE AND FLOATING RESTAURANT, LOBOC TOURISM COMPLEX, BRGY. VILLAFLOR, LOBOC, BOHOL

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONST./IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION, VILLAFLOR CIRCUMFERENTIAL ROAD LEADING TO LOBOC RIVERCRUISE AND FLOATING RESTAURANT, LOBOC TOURISM COMPLEX, BRGY. VILLAFLOR, LOBOC, BOHOL is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱9,459,734.11. Status: Reported complete (DPWH). Contractor on record: FUENTABUILT CONST CORP. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

211 projects · ₱1.8B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF SENIOR HIGH SCHOOL CLASSROOM 4 STOREY 20 CL AT FATIMA NATIONAL SCHOOL, BRGY. FATIMA, GENERAL SANTOS CITY (2UNITS)

South Cotabato 1st DEO, Region XII

2016₱64.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES REHABILITATION OF MULTI-PURPOSE BUILDING, CANDIJAY, BOHOL

Bohol 3rd DEO, Region VII

2023₱61.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM -REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS- JCT. (TER)-JAGNA-SIERRA BULLONES RD - K0069 + 661 - K

Bohol 3rd DEO, Region VII

2022₱58.8M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE LOCAL PROJECTS, LOCAL ROADS AND BRIDGES, LOCAL ROADS, CONSTRUCTION OF ROAD PROTECTION ALONG JCT. (TER) GUINDULMAN - ANDA - BADIANG - COGTONG ROAD, ANDA, BOHOL STA. 20+4

Bohol 3rd DEO, Region VII

2021₱53.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM -REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS-JCT (TER)-JAGNA-SIERRA BULLONES RD - K0082 + 678 - K0

Bohol 3rd DEO, Region VII

2022₱49.6M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-REHAB./RECONST./UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-LOAY INTERIOR ROAD-K0167+337 - K0168+839

Bohol 3rd DEO, Region VII

2024₱48.8M
Reported complete (DPWH)
View all 211 projects →

4. Implementation

Contract Amount

₱9,459,734.11

Progress

Reported complete (DPWH)

Start Date

February 26, 2020

Target End

July 24, 2020

5. Audit