Flood Control and Drainage18J00034

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DISACAN RIVER (UPSTREAM AND DOWNSTREAM) INCLUDING DREDGING, MANUKAN AND JOSE DALMAN, ZAMBOANGA DEL NORTE 1ST DEO, DOWNSTREAM - 0+000.00 - 0+718.00, UPSTREAM - 0+000.00 - 0+360.00, NET LENGTH: 1,078.00 LN.M.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DISACAN RIVER (UPSTREAM AND DOWNSTREAM) INCLUDING DREDGING, MANUKAN AND JOSE DALMAN, ZAMBOANGA DEL NORTE 1ST DEO, DOWNSTREAM - 0+000.00 - 0+718.00, UPSTREAM - 0+000.00 - 0+360.00, NET LENGTH: 1,078.00 LN.M. is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱128,282,203.00. Status: Reported complete (DPWH). Contractor on record: MONTAÑO CONST & DEVELOPMENT CORP. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

30 projects · ₱2.6B total · 0 flags

Other projects by this contractor

View all 30 projects →

4. Implementation

Contract Amount

₱128,282,203.00

Progress

Reported complete (DPWH)

Start Date

March 28, 2018

Target End

November 7, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.