Flood Control and Drainage19LF0084

CONSTRUCTION OF REVETMENT ALONG CATEEL RIVER (SAN ALFONSO SECTION), CATEEL, DAVAO ORIENTAL

CONSTRUCTION OF REVETMENT ALONG CATEEL RIVER (SAN ALFONSO SECTION), CATEEL, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 1st DEO, Region XI. Reported contract value: ₱72,350,762.98. Status: Reported complete (DPWH). Contractor on record: RITZ BUILDERS CONST INC FORMERLY:RITZTOK CONST AND SUPPLY. Figures trace to dpwh.

Davao Oriental 1st DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-19-0003090

₱180,662.00 · FY2019

Released to Regional Field Unit - II (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱72,350,762.98

Progress

Reported complete (DPWH)

Start Date

July 24, 2019

Target End

March 16, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.