Flood Control and Drainage18KI0014

CONSTRUCTION OF FLOOD CONTROL AT ALORAN RIVER, H.Y REGALADO BRIDGE ALONG ALORAN OLD ROUTE, ALORAN, MISAMIS OCCIDENTAL

CONSTRUCTION OF FLOOD CONTROL AT ALORAN RIVER, H.Y REGALADO BRIDGE ALONG ALORAN OLD ROUTE, ALORAN, MISAMIS OCCIDENTAL is a DPWH-tracked public work in Misamis Occidental 1st DEO, Region X. Reported contract value: ₱46,549,941.00. Status: Reported complete (DPWH). Contractor on record: VICTORIANO C LIM CONST CORP FORMERLY: VICTORIANO C LIM CONST. Figures trace to dpwh.

Misamis Occidental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱48,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Aloran River, Aloran, Misamis Occidental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0018857

₱8,639,025.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱46,549,941.00

Progress

Reported complete (DPWH)

Start Date

April 19, 2018

Target End

October 15, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.