Roads24OF0112

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - CONGRESSIONAL AVE (S05266LZ) - K0011+929 - K0011+1234, QUEZON CITY

REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - CONGRESSIONAL AVE (S05266LZ) - K0011+929 - K0011+1234, QUEZON CITY is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱97,997,721.47. Status: Reported complete (DPWH). Contractor on record: DMLC BUILDERS. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure at Barangay Bagbag, Quezon City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quezon City 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

107 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BARANGAY CALAMPINAY COASTAL ROAD (COBCOBAN SECTION), SIPOCOT, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱141.2M
Past target date (DPWH On-Going)

Construction of Flood Control Structure along Estero de Maypajo, Package I, Manila

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region

2024₱113.1M
Reported complete (DPWH)

CLUSTER 9: REPAIR/REHABILITATION OF FLOOD CONTROL/DRAINAGE STRUCTURES,RAGAY, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2024₱112.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO NONOK, BARANGAY MONTAÑEZA - SITIO WALO

Cebu 7th DEO, Region VII

2025₱99.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONSTRUCTION OF REVETMENT ALONG YLANG-YLANG, SAN FRANCISCO, GEN. TRIAS, CAVITE (PHASE III)

Cavite 1st DEO, Region IV-A

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIESCONST OF REVETMENT ALONG RIO GRANDE RIVER RIVER, BARANGAY SANTIAGO, GEN. TRIAS, CAVITE

Cavite 1st DEO, Region IV-A

2024₱99.0M
Past target date (DPWH On-Going)
View all 107 projects →

4. Implementation

Contract Amount

₱97,997,721.47

Progress

Reported complete (DPWH)

Start Date

March 18, 2024

Target End

November 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.