GAA 2025 SSP25DJ0141

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONCRETING OF ROAD WITH BRIDGE AT BRGY. IBABANG TALIM, LUCENA CITY, Q

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) -ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONCRETING OF ROAD WITH BRIDGE AT BRGY. IBABANG TALIM, LUCENA CITY, Q is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱28,808,203.48. Status: Past target date (DPWH On-Going). Contractor on record: DQT BUILDERS CORP FORMERLY DQT BUILDERS 7950. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage Structure, Barangay 10, Lucena City, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱28,808,203.48

Progress

Past target date (DPWH On-Going)

Start Date

September 26, 2025

Target End

July 22, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.