Roads19KC0001

RECONSTRUCTION TO CONCRETE PAVEMENT- ON SPECIFIC LOCATIONS ALONG SAYRE HIGHWAY (S00621MN) K1443+185 TO K1449+000, MANOLO FORTICH, BUKIDNON

RECONSTRUCTION TO CONCRETE PAVEMENT- ON SPECIFIC LOCATIONS ALONG SAYRE HIGHWAY (S00621MN) K1443+185 TO K1449+000, MANOLO FORTICH, BUKIDNON is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP 18310. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

July 1, 2019

Target End

November 30, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.