Flood Control and Drainage22FC0057

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, CALASGASAN-MAGANG-COBANGBANG CREEK, DAET, CAMARINES NORTE

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, CALASGASAN-MAGANG-COBANGBANG CREEK, DAET, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱4,949,813.13. Status: Reported complete (DPWH). Contractor on record: 128 DRAGON CONST AND SUPPLIES. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Mancruz - Pamorangon Creek, Daet, Camarines Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Camarines Norte DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

208 projects · ₱3.4B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ROAD ALONG DAET RIVER, BARANGAY

Region V, Region V

2025₱96.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF BINATAGAN RIVER CONTROL STRUCTURE W/ ROAD (PHASE I)BARA

Region V, Region V

2024₱93.6M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)

Construction of Flood Control Structure along Basud River, Barangay San Jose, Basud, Camarines Norte

BASUD (CAMARINES NORTE), CAMARINES NORTE, Region V

2024₱86.8M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MANGCAMAGONG -MATOOG-TOOG SEAWALL, BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE AND BARANGAY MATOOG-TOOG, MERCEDES, CAMARINES NORTE

Camarines Norte DEO, Region V

2020₱74.9M
Reported complete (DPWH)
View all 208 projects →

4. Implementation

Contract Amount

₱4,949,813.13

Progress

Reported complete (DPWH)

Start Date

March 21, 2022

Target End

May 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.