Buildings and Facilities16FO0053

CONSTRUCTION OF CY 2016 BEFF (BATCH 5), ONE (1) UNIT, ONE (1) CLASSROOM SCHOOL BUILDING, AT TIONGSON ELEMENTARY SCHOOL, LIGAO CITY

CONSTRUCTION OF CY 2016 BEFF (BATCH 5), ONE (1) UNIT, ONE (1) CLASSROOM SCHOOL BUILDING, AT TIONGSON ELEMENTARY SCHOOL, LIGAO CITY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱1,099,797.62. Status: Reported complete (DPWH). Contractor on record: GROSIN CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,099,797.62

Progress

Reported complete (DPWH)

Start Date

August 14, 2016

Target End

November 8, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.