Buildings and Facilities18DE0223

CY 2018 BASIC EDUCATIONAL FACILITIES FUND BATCH 1 - CONSTRUCTION OF 2STY 6CL AT CALUMPIT ELEMENTARY SCHOOL, LOBO, BATANGAS

CY 2018 BASIC EDUCATIONAL FACILITIES FUND BATCH 1 - CONSTRUCTION OF 2STY 6CL AT CALUMPIT ELEMENTARY SCHOOL, LOBO, BATANGAS is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱16,370,419.52. Status: Reported complete (DPWH). Contractor on record: M J APIN BUILDERS. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱39,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Lobo Riverbanks Fabrica, Lobo, Batangas
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-18-0016454

₱15,000,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱16,370,419.52

Progress

Reported complete (DPWH)

Start Date

August 15, 2018

Target End

May 1, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.