Flood Control and Drainage17HJ0002

CONSTRUCTION OF PINOCAWAN FLOOD CONTROL ALONG DUMAGUETE NORTH ROAD, BAGAWINES, VALLEHERMOSO, NEGROS ORIENTAL

CONSTRUCTION OF PINOCAWAN FLOOD CONTROL ALONG DUMAGUETE NORTH ROAD, BAGAWINES, VALLEHERMOSO, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱4,647,480.73. Status: Reported complete (DPWH). Contractor on record: J A CONST AND TRADING CORP FOR: J A CONST 35189. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 35189

33 projects · ₱329.6M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - PREVENTIVE MAINTENANCE-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS-GUIHULNGAN-BALOC-ISABELA RD (S00413NR)-K0126+404-K0126+565,

Negros Oriental 1st DEO, Negros Island Region

2025₱28.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF ONE UNIT FOUR STOREY WORKSHOP BUILDING AT PINOCAUAN HIGH SCHOOL (7.0M X 23M PLUS CORRIDOR 2.50M), VALLEHERMOSO, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2018₱21.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ONE UNIT FOUR STOREY WORKSHOP BUILDING AT LA LIBERTAD TECHNICAL-VOCATIONAL SCHOOL (7.0M X 23M PLUS CORRIDOR 2.50M), LA LIBERTAD, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2018₱20.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF 1-UNIT THREE STOREY TWELVE CLASSROOM SCHOOL BUILDING AT TAGBINO NHS, VALLEHERMOSO, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2016₱17.8M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM: MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF COVERED COURT/EVACUATION CENTER, POBLACION PROPER, VALLEHERMOSO, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2024₱16.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ONE UNIT TWO STOREY SIX CLASSROOM SCHOOL BUILDING AT BINOBOHAN HIGH SCHOOL AT GUIHULNGAN, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2019₱16.1M
Reported complete (DPWH)
View all 33 projects →

4. Implementation

Contract Amount

₱4,647,480.73

Progress

Reported complete (DPWH)

Start Date

March 9, 2017

Target End

June 16, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.