Buildings and Facilities24E00215

MARINDUQUE STATE COLLEGE- CONST. OF A SUB-SURFACE COMBINED DRAINAGE SYSTEMS, PHASE II, TANZA, BOAC, MARINDUQUE

MARINDUQUE STATE COLLEGE- CONST. OF A SUB-SURFACE COMBINED DRAINAGE SYSTEMS, PHASE II, TANZA, BOAC, MARINDUQUE is a DPWH-tracked public work in Region IV-B, Region IV-B. Reported contract value: ₱9,312,649.68. Status: Past target date (DPWH On-Going). Contractor on record: K CONST. Figures trace to dpwh.

Region IV-B, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,312,649.68

Progress

Past target date (DPWH On-Going)

Start Date

September 25, 2024

Target End

April 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.