Construction of Flood Mitigation Structure22FB0128

Construction of River Bank Protection Works and Drainage System along Brgy. Taysan River Legazpi City

Construction of River Bank Protection Works and Drainage System along Brgy. Taysan River Legazpi City is a DPWH-tracked public work in LEGAZPI CITY (CAPITAL) (ALBAY), ALBAY, Region V. Reported contract value: ₱48,999,560.94. Status: Reported complete (DPWH). Contractor on record: WELEX CONST INC FORMERLY WELEX C. Figures trace to sumbong.

LEGAZPI CITY (CAPITAL) (ALBAY), ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Panal River, Puting Daga Barangay 18 Cabangan Camiri, Brgy. 15 Ilawod East Section, Legazpi City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001737

₱187,700,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002950

₱120,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001730

₱80,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001631

₱60,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002890

₱2,150,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002436

₱47,688,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001623

₱40,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001966

₱40,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001965

₱20,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003024

₱50,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,999,560.94

Progress

Reported complete (DPWH)

Start Date

April 11, 2022

Target End

October 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.