Flood Control and Drainage24CL0217

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTO TOMAS RIVER (MACULCOL DIKE), PHASE 5, SAN NARCISO, ZAMBALES

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTO TOMAS RIVER (MACULCOL DIKE), PHASE 5, SAN NARCISO, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱93,058,254.19. Status: Reported complete (DPWH). Contractor on record: NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST 15104. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Omaya River, San Narciso, Zambales ( Phase 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zambales 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱93,058,254.19

Progress

Reported complete (DPWH)

Start Date

January 9, 2025

Target End

December 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.