Roads20C00019

ASSET PRESERVATION PROGRAM-REHABILITITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS, JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA

ASSET PRESERVATION PROGRAM-REHABILITITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS, JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱151,097,207.76. Status: Reported complete (DPWH). Contractor on record: B-12 CONST AND TRADING CORP. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

164 projects · ₱8.7B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-JOSE ABAD SANTOS AVENUE (JASA), PROVINCE OF PAMPANGA

Region III, Region III

2023₱156.3M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS / FACILITIES - REHABILITATION OF STA. ANA - MAGALANG ROAD (SAN PABLO - ARENAS PORTION) PHASE I,

Pampanga 1st DEO, Region III

2025₱137.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF DEL ROSARIO - CALULUT ROAD, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱137.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT-ROAD WIDENING-PRIMARY ROADS, JOSE ABAD SANTOS AVENUE (JASA), PAMPANGA 2ND LEGISLATIVE DISTRICT, PROVINCE OF PAMPANGA

Region III, Region III

2018₱132.6M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - MALINO - SUCLABAN BYPASS ROAD, CITY OF SAN FERNANDO, PAMPANGA

Pampanga 1st DEO, Region III

2025₱130.7M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - JOSE ABAD SANTOS AVENUE (JASA) S01195LZ - K0071+(-445) - K0072+391

Pampanga 1st DEO, Region III

2025₱130.6M
Reported complete (100% progress, DPWH status On-Going)
View all 164 projects →

4. Implementation

Contract Amount

₱151,097,207.76

Progress

Reported complete (DPWH)

Start Date

December 13, 2020

Target End

October 8, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.