Buildings and Facilities22FK0106

CLUSTER XLV-CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS_ FACILITIES TO SUPPORT SOCIAL SERVICES- 1.) CONSTRUCTION OF MULTI-PURPOSE FACILITIES, SORSOGON NATIONAL HIGH SCHOOL 2.) CONSTRUCTION OF M

CLUSTER XLV-CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS_ FACILITIES TO SUPPORT SOCIAL SERVICES- 1.) CONSTRUCTION OF MULTI-PURPOSE FACILITIES, SORSOGON NATIONAL HIGH SCHOOL 2.) CONSTRUCTION OF M is a DPWH-tracked public work in Sorsogon DEO, Region V. Reported contract value: ₱19,383,071.70. Status: Reported complete (DPWH). Contractor on record: CHEEREL CONST. Figures trace to dpwh.

Sorsogon DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure and Embankment of Lungib Seawall, Casiguran, Sorsogon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Sorsogon DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

18 projects · ₱459.5M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239-ROAD SAFETY FEATURES/DEVICES ALONG NATIONAL ROADS AND BRIDGES-INSTALLATION OF SOLAR STREET LIGHTS ALONG DAANG MAHARLIKA (LZ)-K0540+(-547)-K0554+

Region V, Region V

2024₱141.1M
Past target date (DPWH On-Going)
No sat.

CLUSTER XIII -LOCAL INFRASTRUCTURE PROGRAM BUILDINGS AND OTHER STRUCTURES/REHABILITATION OF MULTI-PURPOSE BUILDING RURAL HEALTH UNIT IN MAGALLANES, DONSOL AND SORSOGON CITY

Sorsogon DEO, Region V

2021₱29.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND_OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR_STRATEGIC PUBLIC BUILDINGS_FACILITIES-CONSTRUCTION OF GIMALOTO BRIDGE, BRGY.

Sorsogon DEO, Region V

2023₱28.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, BRGY. MALINAO TO

Sorsogon DEO, Region V

2023₱28.4M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0250+193-K0250+398, K0250+509-K0250+719, K0250+832-K0250+910, STA. ELENA, CAMARINES NORTE (1ST LEGISLATIVE D

Region V, Region V

2025₱25.9M
Past target date (DPWH On-Going)
No sat.

WIDENING OF PERMANENT BRIDGES, AROPAG BR. (B00169LZ) ALONG JCT. ABUYOG - GUBAT - ARIMAN RD, GUBAT, S

Sorsogon 2nd DEO, Region V

2020₱24.8M
Reported complete (DPWH)
View all 18 projects →

4. Implementation

Contract Amount

₱19,383,071.70

Progress

Reported complete (DPWH)

Start Date

August 16, 2022

Target End

December 13, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.