Roads17GP0016

CONCRETING OF BARANGAY ROAD WITH SLOPE PROTECTION AT BRGY. SAN MIGUEL, DUMALAG, CAPIZ

CONCRETING OF BARANGAY ROAD WITH SLOPE PROTECTION AT BRGY. SAN MIGUEL, DUMALAG, CAPIZ is a DPWH-tracked public work in Capiz 2nd DEO, Region VI. Reported contract value: ₱9,358,157.76. Status: Reported complete (DPWH). Contractor on record: MBM CONST 37891. Figures trace to dpwh.

Capiz 2nd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,358,157.76

Progress

Reported complete (DPWH)

Start Date

April 12, 2017

Target End

July 17, 2017