Flood Control and Drainage18MC0106

CONSTRUCTION OF MARBEL RIVER FLOOD CONTROL, MATALAM, NORTH COTABATO STA. 4+077-STA. 4+401 L=324 LM RIGHT BANK

CONSTRUCTION OF MARBEL RIVER FLOOD CONTROL, MATALAM, NORTH COTABATO STA. 4+077-STA. 4+401 L=324 LM RIGHT BANK is a DPWH-tracked public work in Cotabato 2nd DEO, Region XII. Reported contract value: ₱29,399,000.00. Status: Reported complete (DPWH). Contractor on record: JARGON CONST. Figures trace to dpwh.

Cotabato 2nd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Lisbong River Riprap/Riverbank Protection (Tamontaka 4, right side), Cotabato City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-18-0000713

₱20,551,000.00 · FY2018

Released to Tubod National High School (Camp 7 To NHS Extension) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,399,000.00

Progress

Reported complete (DPWH)

Start Date

February 26, 2018

Target End

October 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.