Buildings and Facilities19J00097

CONSTRUCTION OF MULTIPURPOSE BUILDING, BARANGAY BATU-BATU, PANGLIMA SUGALA, TAWI-TAWI

CONSTRUCTION OF MULTIPURPOSE BUILDING, BARANGAY BATU-BATU, PANGLIMA SUGALA, TAWI-TAWI is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱48,857,912.94. Status: Reported complete (DPWH). Contractor on record: NURBEN ENGINEERING AND BUILDING CONTRACTOR. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱48,857,912.94

Progress

Reported complete (DPWH)

Start Date

August 9, 2019

Target End

January 23, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.