Buildings and Facilities23EF0107

CONST. OF 2STY4CL, LABOG ELEMENTARY SCHOOL (BATCH 1), SOFRONIO ESPAÑOLA, PALAWAN

CONST. OF 2STY4CL, LABOG ELEMENTARY SCHOOL (BATCH 1), SOFRONIO ESPAÑOLA, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱14,998,822.09. Status: Reported complete (DPWH). Contractor on record: HARDROCKPLATINUM DEVELOPMENT CORP. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Abo-Abo River Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 200 B/S Upstream, Barangay Abo-Abo, Sofronio Espa±ola, Palawan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Palawan 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,998,822.09

Progress

Reported complete (DPWH)

Start Date

August 17, 2023

Target End

June 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.