Roads22CD0109

CONSTRUCTION OF ROAD GOING TO DAANG MAHARLIKA HIGHWAY, BRGY. STA. CATALINA BATA SAN ILDEFONSO, BULACAN

CONSTRUCTION OF ROAD GOING TO DAANG MAHARLIKA HIGHWAY, BRGY. STA. CATALINA BATA SAN ILDEFONSO, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱4,815,605.71. Status: Reported complete (DPWH). Contractor on record: EMICA BUILDERS AND SUPPLY 42099. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Daang Maharlika Road at Tigpalas Creek, San Miguel, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bulacan 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 42099

53 projects · ₱670.1M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRA. PROGRAM (BIP) - BIP - MULTI-PURPOSE BLDGS./ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING SAPANG PUTIK ELEMENTARY SCHOOL, BARANGAY SAPANG PUTIK, SAN ILDEFONSO, BULACAN

Bulacan 3rd DEO, Region III

2025₱43.9M
Ongoing (DPWH-reported)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - BIP - MULTI -PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING AT UPIG ELEMENTARY SCHOOL, BARANGAY UPIG, SAN ILDEFONSO, BULACAN

Region III, Region III

2024₱39.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, CALUMPANG ELEMENTARY SCHOOL, SAN MIGUEL, BULACAN

Bulacan 3rd DEO, Region III

2025₱34.1M
Ongoing (DPWH-reported)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM-BIP-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHABILITATION OF DRAINAGE FACILITIES (MARONQUILLO AND TALACSAN), SAN RAFAEL,BULACAN

Region III, Region III

2024₱24.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, DILIMAN, SAN RAFAEL, BULACAN

Region III, Region III

2023₱19.8M
Reported complete (DPWH)
No sat.

CONVERG. AND SPECIAL SUPPORT PROGRAM- BASIC INFRA. PROGRAM (BIP)-BIP-ACCESS ROADS AND/OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/STRAT. PUBLIC BLDGS./ FACILITIES-CONST. OF ROAD AT SITIO KAMBUBUYUGAN, BRGY. KALAWAKAN, DONA REMEDIOS TRINIDAD, BULACAN

Bulacan 3rd DEO, Region III

2025₱19.5M
Ongoing (DPWH-reported)
View all 53 projects →

4. Implementation

Contract Amount

₱4,815,605.71

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

April 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.