Roads16MB0026

COMPLETION/REPAIR/REHABILITAION/IMPROVEMENT/CONSTRUCTION OF PEDESTRIAN OVERPASSES, MAKAR-KIAMBA ROAD, FRONT OF STA. TERESITA CHURCH, BRGY. POBLACION, TUPI, SOUTH COTABATO (S00253MN), PHASE II, K1687+298

COMPLETION/REPAIR/REHABILITAION/IMPROVEMENT/CONSTRUCTION OF PEDESTRIAN OVERPASSES, MAKAR-KIAMBA ROAD, FRONT OF STA. TERESITA CHURCH, BRGY. POBLACION, TUPI, SOUTH COTABATO (S00253MN), PHASE II, K1687+298 is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱5,134,402.89. Status: Reported complete (DPWH). Contractor on record: GEMMA CONST SUPPLY INC FORMERLY:GEMMA CON. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,134,402.89

Progress

Reported complete (DPWH)

Start Date

April 25, 2016

Target End

August 2, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.