Roads23GG0155

PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO - CAPIZ (NEW ROUTE) K0036+433 - K0037+100, K0037+200 - K0037+500, K0037+600 - K0038+150, K0038+350 - K0038+800, K0038+950 - K0039+554

PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO - CAPIZ (NEW ROUTE) K0036+433 - K0037+100, K0037+200 - K0037+500, K0037+600 - K0038+150, K0038+350 - K0038+800, K0038+950 - K0039+554 is a DPWH-tracked public work in Iloilo 2nd DEO, Region VI. Reported contract value: ₱56,673,768.44. Status: Reported complete (DPWH). Contractor on record: EAST ASIA CONST INC. Figures trace to dpwh.

Iloilo 2nd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Jalaur River, Calinog, Iloilo
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Iloilo 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱56,673,768.44

Progress

Reported complete (DPWH)

Start Date

February 22, 2023

Target End

June 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.