GAA 2025 DA FMR25IK0034

CONCRETING OF BRGY. BACYARAN TO BRGY. BULAO FMR, BRGY. BACYARAN AND BRGY. BULAO, CALBIGA, SAMAR

CONCRETING OF BRGY. BACYARAN TO BRGY. BULAO FMR, BRGY. BACYARAN AND BRGY. BULAO, CALBIGA, SAMAR is a DPWH-tracked public work in Samar 2nd DEO, Region VIII. Reported contract value: ₱14,904,993.06. Status: Past target date (DPWH On-Going). Contractor on record: ETAN CONST. Figures trace to dpwh.

Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Calbiga Flood Control Structure, along Calbiga river, Barangay Barobaybay, Calbiga, Samar
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Samar 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

138 projects · ₱4.2B total · 0 flags

4. Implementation

Contract Amount

₱14,904,993.06

Progress

Past target date (DPWH On-Going)

Start Date

May 26, 2025

Target End

September 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.